District of Columbia PFAS Regulations: Federal Limits and a Federally Operated Supply

Federal MCL with the Washington Aqueduct as treatment provider, DC Water as distributor and EPA Region 3 as primacy agency.

The District applies the federal drinking water rule, with a structure no state shares: its water is treated by a federal agency, distributed by a regional authority and regulated directly by EPA Region 3.

Agency

EPA Region 3 (primacy); DC Water and the Washington Aqueduct for supply; DOEE for site and surface water work

Primary Statute

40 CFR 141 Subpart Z applied directly; DC Municipal Regulations Title 21 for environmental programmes

Rule Adopted

Federal rule effective 25 June 2024

Compliance

2029-04-26

Context

Regulatory Overview

The District has no state MCL and no state primacy. EPA Region 3 regulates drinking water in DC directly. The federal MCLs of 4 ppt for PFOA and PFOS, 10 ppt each for PFHxS, PFNA and HFPO-DA, and a hazard index of 1 for the mixture took effect on 25 June 2024. Initial monitoring is due by 2027 and compliance by 26 April 2029.

The supply chain is unusual. The Washington Aqueduct, operated by the US Army Corps of Engineers, draws from the Potomac and treats the water. DC Water distributes it. Responsibility for meeting a PFAS MCL therefore sits across a federal operator and a local authority, which makes coordination part of the compliance problem rather than an afterthought.

On the site side, DOEE handles contaminated land and surface water within the District. Joint Base Anacostia-Bolling and the Anacostia River legacy are the significant PFAS-relevant locations, and the Anacostia already carries decades of remediation attention for other contaminants. Land is scarce and dense, so any remedy has to work in a tight urban footprint with neighbours on all sides.

Numbers

State MCL vs Federal MCL

Compound

District of Columbia

Federal (2024 NPDWR)

Note

PFOANo state MCL4 pptFederal MCL controls, compliance 26 April 2029

PFOSNo state MCL4 pptFederal MCL controls

PFHxSNo state MCL10 ppt

PFNANo state MCL10 ppt

HFPO-DA (GenX)No state MCL10 ppt

MixtureNo state valueHI ≤ 1PFHxS, PFNA, HFPO-DA and PFBS combined

PrimacyNo District primacyEPA Region 3 regulates directlyUnique among the jurisdictions covered

ppt = parts per trillion (ng/L). Where a state number is stricter, the state number controls; where the federal number is stricter, the federal number controls for public water systems.

History

Rulemaking & Response Timeline

2016-05EPA issues the 70 ppt lifetime health advisory for PFOA and PFOS combined, the first national number utilities worked to.

2021-10EPA publishes the PFAS Strategic Roadmap, committing to a drinking water rule, CERCLA designation and effluent guidelines.

2021-2023Washington Aqueduct PFAS monitoring and reporting expand as UCMR 5 and rule development proceed.

2022-2024Joint Base Anacostia-Bolling and Anacostia River investigations continue alongside long-running river restoration work.

2023-01UCMR 5 monitoring begins, putting 29 PFAS analytes into routine sampling at large and selected small systems.

2024-04-10EPA finalises the PFAS National Primary Drinking Water Regulation, 89 FR 32532.

2024-06-25The federal rule takes effect in this state, with initial monitoring due by 2027 and compliance by 26 April 2029.

2026-05-18EPA proposes changes to parts of the 2024 rule. Those changes are not final, and the 2024 values remain the ones to plan against.

Case Docket

Notable Enforcement & Response Cases

ongoing

Washington Aqueduct supply

A federally operated treatment plant supplying a local distributor. Compliance planning has to work across two organisations with different funding and procurement processes.

ongoing

Joint Base Anacostia-Bolling

Fire training history on a dense urban installation next to a river already under restoration. Site work is constrained by space more than by technology.

ongoing

Anacostia River sediment

Decades of sediment remediation attention means PFAS enters a programme that is already active, which shortens the path from finding to action.

Compliance

Permit & Cleanup Pathways

Site liability runs through the state voluntary cleanup or remediation programme and, where PFOA or PFOS are present, through CERCLA following the 2024 hazardous substance designation.

Federal facilities work under CERCLA and the Defense Environmental Restoration Program, so the schedule and the funding follow the military service rather than the state permit calendar.

Spent granular activated carbon, ion exchange resin and impacted soil move under the state solid and hazardous waste rules. No PFAS-specific waste listing applies, which makes the disposal facility's own acceptance criteria the practical constraint.

On site thermal treatment needs a state air authorisation. Applications carry better when they include stack testing evidence and destruction data from comparable PFAS work.

DOEE administers the District's contaminated site and voluntary cleanup programmes, and any river-adjacent work touches the existing Anacostia restoration framework.

Urban density means access, traffic and noise constraints shape the remedy as much as the contamination does.

Obligations

Sampling & Reporting

Initial monitoring for all 6 regulated PFAS is due by 2027, quarterly for surface water systems and for groundwater systems serving more than 10,000 people, with reduced schedules available once results are consistently low.

Compliance is measured on a running annual average at each entry point to the distribution system, so a single quarter above the MCL can be carried by later clean quarters and a single clean quarter cannot rescue a bad year.

Public notice and reporting in the Consumer Confidence Report start once a system is in violation, and utilities that wait until 2029 to find out lose the years they would need to design and build treatment.

Laboratories must run EPA Method 533 or 537.1 for compliance samples. Site investigation work commonly uses Method 1633 for the wider analyte list in soil, sludge and wastewater.

Where a supply is treated by one entity and distributed by another, sampling responsibilities and data sharing should be documented rather than assumed.

FAQ

Frequently Asked Questions

Who regulates drinking water in the District?
EPA Region 3 directly, because the District does not hold primacy. The federal MCLs apply without a local overlay.
Who is responsible for PFAS treatment in DC?
The Washington Aqueduct, operated by the Army Corps of Engineers, treats the water, and DC Water distributes it. Any treatment upgrade has to be planned across both.
What are the main PFAS sites in the District?
Joint Base Anacostia-Bolling and locations connected to the Anacostia River are the significant ones. Both sit inside a dense urban area with limited working space.

Primary Sources

Data not supplied by Nelson. Every figure comes from public regulator records published by the agencies cited. Nelson compiles, maps and links the records, and does not create, verify, adjust or own the underlying data. This hub is a free public resource published to share knowledge. Every figure traces to a government dataset a reader can download and re-check, the sources are listed in the methodology, and nothing here is gated behind a form. Dataset compilation copyright 2026 Nelson Environmental Remediation Ltd. All rights reserved. Source attribution required for reuse. Data licence and citation.

DC DOEE

DC Water

US EPA, PFAS National Primary Drinking Water Regulation (2024)

US Department of Defense, PFAS cleanup and AFFF transition reporting

Other State Briefs

ALAlabamaFederal MCL implemented by ADEM; the pressure comes from Decatur-area manufacturing history and AFFF sites, not from a state number.

AKAlaskaFederal MCL for drinking water, state cleanup levels under 18 AAC 75, and logistics that make on site treatment the practical answer.

AZArizonaFederal MCL implemented by ADEQ, backed by one of the more thorough state sampling programmes and a long-running Tucson-area groundwater plume.

ARArkansasFederal MCL only; the site work sits at Little Rock Air Force Base, Ebbing Air National Guard Base and industrial legacy properties.

CACaliforniaSix-analyte notification framework; state MCLs in rulemaking; DTSC designating PFAS-containing wastes as hazardous.

COColoradoReg 31 groundwater and surface water standards; no state drinking water MCL; HB22-1345 product bans; Peterson SFB / Widefield AFFF community response ongoing.

See all 51 US jurisdictions in the PFAS Regulatory Tracker →

Contact

How can we help?

Project inquiries, technical consultation, or emergencies.

We respond to project inquiries within one business day.

Nelson Environmental Remediation

Head Office

30541 - 100 Avenue

Acheson (Edmonton), Alberta

Canada T7X 6L8

Phone

1.780.960.3660

Toll Free: 1.888.960.8222

Fax

1.780.962.6885

Email

Follow Us on LinkedIn →

More from Nelson

  • Mobile thermal technology: configured for the material, brought to site
  • How to use The Hub for contamination research
  • Navigator: a practical guide to remediation strategy
  • The Ground Truth: Warren Nelson's remediation newsletter
  • A new era of enlightenment
  • Value should be the final outcome
  • What’s next at Nelson
  • Why independent research matters more than anything
  • Over thirty years of permanent outcomes: a field review of Nelson’s project record
  • Petroleum-contaminated soil treatment in the US: build the plan around the fuel profile
  • Contaminated soil management in the US: from excavation to an accepted destination
  • US remediation project evidence: what Tioga and Honolulu tell a project owner

Site Navigation

  • All Articles & Research
  • Thermal Remediation Capabilities
  • Project Case Studies
  • Remediation Glossary
  • About Nelson Environmental Remediation
  • Contact Nelson