PFAS Regulatory Tracker

CA

State Regulatory Brief

EPA Region 9

California PFAS Regulations: The Notification-Level Regime & What's Coming Next

Six-analyte notification framework; state MCLs in rulemaking; DTSC designating PFAS-containing wastes as hazardous.

California operates the country's most granular PFAS notification framework and is preparing its own MCLs on top of the 2024 federal rule. Public water systems already report against six PFAS analytes; enforcement bites at the treatment obligation, not just the number.

Agency

State Water Resources Control Board, Division of Drinking Water (DDW); CalEPA/DTSC for waste

Primary Statute

Health & Safety Code §116400 et seq.; 22 CCR Div. 4; DTSC 22 CCR §66261

Rule Adopted

Notification & Response Levels: 2019 to 2020; federal MCL enforceable 2029

Compliance

2029-04-26 (federal MCL) (EPA proposed changes on 18 May 2026 that are not final)

Context

Regulatory Overview

California treats PFAS as a treatment-forcing pollutant, not just a monitoring one. When a public water system exceeds a Notification Level it must notify the governing body of the local agency; when it exceeds the Response Level, DDW expects the system to take the source out of service or install treatment. The state's approach is faster and more compound-specific than the federal MCL and will persist alongside the EPA rule.

DTSC has independently designated certain PFAS-containing wastes as hazardous under California's more protective waste code. That drives disposal and destruction economics: AFFF-impacted soils, spent GAC, and IX resins from PFAS treatment are frequently non-RCRA hazardous in California even when they are not RCRA hazardous federally. Destruction (thermal or SCWO) becomes the compliant off-ramp.

The California OEHHA Public Health Goals for PFOA (0.007 ppt) and PFOS (1 ppt) are non-enforceable but signal the direction of the pending state MCL. Utilities and industrial dischargers should plan around a state MCL at or below the federal number. California has not adopted a state PFAS MCL; Notification Levels and Response Levels are advisory, not enforceable MCLs. DDW issued new and revised levels for PFOA, PFOS, PFHxS and PFHxA on October 29, 2025, and those four values are shown below. Earlier levels for PFBS, PFNA and PFHpA were not part of that revision and are withheld until they are confirmed against the live DDW table.

Numbers

State MCL vs Federal MCL

Compound

California

Federal (2024 NPDWR)

Note

PFOA4 (NL) / 10 (RL)4 pptRevised 29 October 2025; levels act as treatment triggers

PFOS4 (NL) / 40 (RL)4 pptRevised 29 October 2025

PFHxS3 (NL) / 10 (RL)10 pptState NL stricter than federal MCL

PFHxA1,000 (NL) / 10,000 (RL)Not regulatedState-only analyte

ppt = parts per trillion (ng/L). Where a state number is stricter, the state number controls; where the federal number is stricter, the federal number controls for public water systems.

History

Rulemaking & Response Timeline

2019-08DDW issues first PFOA/PFOS notification levels (5.1 / 6.5 ppt).

2020-02Response Levels adopted; utilities compelled to treat or shut down sources.

2021-07Additional NLs for PFBS, PFHxS, PFNA, PFHpA.

2025-10DDW issues new and revised NLs and RLs for PFOA, PFOS, PFHxS and PFHxA.

2022-09AB 1200 & AB 2771, PFAS bans in food packaging & cosmetics.

2023-01SB 502 phased AFFF restrictions in effect.

2024-06Federal PFAS NPDWR effective; layered onto state framework.

2025-2026OEHHA finalizing Public Health Goals; state MCL rulemaking initiated.

Case Docket

Notable Enforcement & Response Cases

2020 to date

Orange County Water District (OCWD) treatment build-out

Following NL/RL exceedances across dozens of wells in the OCWD service area, retail agencies (Anaheim, Fullerton, Garden Grove, Santa Ana, others) executed a coordinated $1B+ IX/GAC treatment program under DDW oversight. The response level regime was the operative driver.

Public source

2021 to 2024

Cal Water, Chico, Bakersfield, Livermore treatment installations

California Water Service installed GAC systems on multiple wells that exceeded response levels; costs are being recovered through the PFAS Memorandum Account authorized by the CPUC.

ongoing

Fresno Trap Range & Castle AFB (Merced), DoD remediation

Long-tail AFFF plumes under active investigation by USACE / Air Force with DDW oversight; multiple municipal wellheads offline pending treatment.

Compliance

Permit & Cleanup Pathways

Waste Discharge Requirements (WDRs) under Porter-Cologne for on-site treatment residuals.

Non-RCRA hazardous waste manifesting under Cal Code §66261 for spent media & AFFF-impacted soils.

Air permits from the local AQMD for thermal destruction / regeneration units.

Coordination with DDW on treatment approvals for potable reuse of treated water.

Obligations

Sampling & Reporting

Quarterly UCMR 5 sampling for large PWS through 2025; ongoing state-level monitoring per DDW Order.

Source-water sampling frequency escalates on any RL exceedance.

Industrial dischargers face NPDES PFAS monitoring conditions in updated permits.

FAQ

Frequently Asked Questions

Is California's PFAS notification level enforceable?
Notification Levels themselves are health-based advisory triggers; the enforcement teeth come from the Response Level, which obligates the public water system to remove the source from service or install treatment. Utilities that ignore an RL exceedance face DDW compliance orders.
Do I need a hazardous-waste manifest for PFAS-impacted soil in California?
In many cases, yes. DTSC's non-RCRA hazardous designations can apply to PFAS-containing waste streams even where federal RCRA rules do not. Confirm waste characterization before disposal or transport.
How does the pending state MCL relate to the 2024 federal MCL?
California is expected to adopt state MCLs at or below the federal values, with the state MCL controlling where stricter. The federal rule sets a national floor; California typically operates above that floor.

Primary Sources

Data not supplied by Nelson. Every figure comes from public regulator records published by the agencies cited. Nelson compiles, maps and links the records, and does not create, verify, adjust or own the underlying data. This hub is a free public resource published to share knowledge. Every figure traces to a government dataset a reader can download and re-check, the sources are listed in the methodology, and nothing here is gated behind a form. Dataset compilation copyright 2026 Nelson Environmental Remediation Ltd. All rights reserved. Source attribution required for reuse. Data licence and citation.

SWRCB PFAS Program

DDW Notification & Response Levels

DTSC PFAS Waste Guidance

OEHHA PFAS Public Health Goals

US EPA PFAS NPDWR (2024)

Other State Briefs

ALAlabamaFederal MCL implemented by ADEM; the pressure comes from Decatur-area manufacturing history and AFFF sites, not from a state number.

AKAlaskaFederal MCL for drinking water, state cleanup levels under 18 AAC 75, and logistics that make on site treatment the practical answer.

AZArizonaFederal MCL implemented by ADEQ, backed by one of the more thorough state sampling programmes and a long-running Tucson-area groundwater plume.

ARArkansasFederal MCL only; the site work sits at Little Rock Air Force Base, Ebbing Air National Guard Base and industrial legacy properties.

COColoradoReg 31 groundwater and surface water standards; no state drinking water MCL; HB22-1345 product bans; Peterson SFB / Widefield AFFF community response ongoing.

CTConnecticutSix-compound 10 ng/L drinking-water action level; PFAS Roadmap product phase-outs; Bradley IAP AFFF spill precedent.

See all 51 US jurisdictions in the PFAS Regulatory Tracker →

Contact

How can we help?

Project inquiries, technical consultation, or emergencies.

We respond to project inquiries within one business day.

Nelson Environmental Remediation

Head Office

30541 - 100 Avenue

Acheson (Edmonton), Alberta

Canada T7X 6L8

Phone

1.780.960.3660

Toll Free: 1.888.960.8222

Fax

1.780.962.6885

Email

Follow Us on LinkedIn →

More from Nelson

  • PFAS and the changing landscape: What site owners should know
  • LNAPL remediation regulations: How to identify the requirements for your site
  • Alberta Tier 1 soil and groundwater remediation guidelines: How to assess their applicability
  • Mobile thermal technology: configured for the material, brought to site
  • How to use The Hub for contamination research
  • Navigator: a practical guide to remediation strategy
  • The Ground Truth: Warren Nelson's remediation newsletter
  • A new era of enlightenment
  • Value should be the final outcome
  • What’s next at Nelson
  • Why independent research matters more than anything
  • Over thirty years of permanent outcomes: a field review of Nelson’s project record

Site Navigation

  • All Articles & Research
  • Thermal Remediation Capabilities
  • Project Case Studies
  • Remediation Glossary
  • About Nelson Environmental Remediation
  • Contact Nelson