Federal MCL plus the 2023 PFAS Protection Act; the Parkersburg C8 legacy is the origin point of US PFAS science.

West Virginia is where PFAS became a public issue in the United States. The Parkersburg C8 litigation produced the health studies that everything since has been built on, and the state now runs source water sampling under its own PFAS Protection Act alongside the federal MCLs.

Agency

West Virginia Department of Health, Bureau for Public Health; WVDEP for source water and site work

Primary Statute

PFAS Protection Act (2023); 64 CSR 3 incorporating 40 CFR 141 Subpart Z

Rule Adopted

PFAS Protection Act 2023; federal rule effective 25 June 2024

Compliance

2029-04-26

Context

Regulatory Overview

West Virginia applies the federal PFAS MCLs and has its own statute on top of them. The federal MCLs of 4 ppt for PFOA and PFOS, 10 ppt each for PFHxS, PFNA and HFPO-DA, and a hazard index of 1 for the mixture took effect on 25 June 2024. Initial monitoring is due by 2027 and compliance by 26 April 2029. The state's PFAS Protection Act, enacted in 2023, put source water sampling and source identification duties into state law rather than leaving them to guidance.

The Parkersburg story is the reason PFAS is regulated anywhere. Discharges of PFOA from the Washington Works plant into the Ohio River and surrounding communities led to litigation, a medical monitoring programme and the C8 Health Project, which produced the epidemiological work that later health advisories and MCLs relied on. That history means West Virginia communities have been living with PFAS knowledge for longer than the regulators have.

The practical effect today is a state where source identification is expected rather than optional. WVDEP and the state's source water study located the industrial and military contributors ahead of the federal rule, and the PFAS Protection Act built on that by requiring utilities to sample raw water and by connecting results back to source reduction.

Numbers

State MCL vs Federal MCL

Compound

West Virginia

Federal (2024 NPDWR)

Note

PFOANo state MCL4 pptFederal MCL controls, compliance 26 April 2029

PFOSNo state MCL4 pptFederal MCL controls

PFHxSNo state MCL10 ppt

PFNANo state MCL10 ppt

HFPO-DA (GenX)No state MCL10 ppt

MixtureNo state valueHI ≤ 1PFHxS, PFNA, HFPO-DA and PFBS combined

Source water samplingRequired by the PFAS Protection ActNo equivalent requirementState law requires raw water sampling and source identification

ppt = parts per trillion (ng/L). Where a state number is stricter, the state number controls; where the federal number is stricter, the federal number controls for public water systems.

History

Rulemaking & Response Timeline

2001-2017Parkersburg C8 litigation, the C8 Health Project and subsequent settlements produce the epidemiology that underpins later PFAS health assessments.

2016-05EPA issues the 70 ppt lifetime health advisory for PFOA and PFOS combined, the first national number utilities worked to.

2020-2021WVDEP and partners complete a statewide PFAS source water study identifying industrial and military contributors.

2021-10EPA publishes the PFAS Strategic Roadmap, committing to a drinking water rule, CERCLA designation and effluent guidelines.

2023-01UCMR 5 monitoring begins, putting 29 PFAS analytes into routine sampling at large and selected small systems.

2023-03West Virginia enacts the PFAS Protection Act, requiring source water sampling and source identification.

2024-04-10EPA finalises the PFAS National Primary Drinking Water Regulation, 89 FR 32532.

2024-06-25The federal rule takes effect in this state, with initial monitoring due by 2027 and compliance by 26 April 2029.

2026-05-18EPA proposes changes to parts of the 2024 rule. Those changes are not final, and the 2024 values remain the ones to plan against.

Case Docket

Notable Enforcement & Response Cases

2001 onward

Parkersburg and Washington Works

The origin case for US PFAS regulation. Litigation produced medical monitoring, a large health study and settlements, and it established that PFOA exposure had measurable population health effects.

2020-2021

Statewide source water study

A systematic look at raw water across the state, which located contributors rather than only measuring outcomes. It became the evidence base for the PFAS Protection Act.

2023 onward

PFAS Protection Act implementation

Source water sampling duties and source identification connect a utility's result back to the facility responsible, which is what makes reduction possible instead of just treatment.

Compliance

Permit & Cleanup Pathways

Site liability runs through the state voluntary cleanup or remediation programme and, where PFOA or PFOS are present, through CERCLA following the 2024 hazardous substance designation.

Federal facilities work under CERCLA and the Defense Environmental Restoration Program, so the schedule and the funding follow the military service rather than the state permit calendar.

Spent granular activated carbon, ion exchange resin and impacted soil move under the state solid and hazardous waste rules. No PFAS-specific waste listing applies, which makes the disposal facility's own acceptance criteria the practical constraint.

On site thermal treatment needs a state air authorisation. Applications carry better when they include stack testing evidence and destruction data from comparable PFAS work.

WVDEP permits are the route to source reduction, and the PFAS Protection Act ties utility sampling results into that process.

Site closure runs through WVDEP's voluntary remediation programme, with CERCLA exposure for PFOA and PFOS following the 2024 designation.

Obligations

Sampling & Reporting

Initial monitoring for all 6 regulated PFAS is due by 2027, quarterly for surface water systems and for groundwater systems serving more than 10,000 people, with reduced schedules available once results are consistently low.

Compliance is measured on a running annual average at each entry point to the distribution system, so a single quarter above the MCL can be carried by later clean quarters and a single clean quarter cannot rescue a bad year.

Public notice and reporting in the Consumer Confidence Report start once a system is in violation, and utilities that wait until 2029 to find out lose the years they would need to design and build treatment.

Laboratories must run EPA Method 533 or 537.1 for compliance samples. Site investigation work commonly uses Method 1633 for the wider analyte list in soil, sludge and wastewater.

Raw water sampling is a state duty in West Virginia, not just good practice. Finished water alone does not satisfy the source identification purpose of the statute.

FAQ

Frequently Asked Questions

What does the PFAS Protection Act require?
It puts source water sampling and source identification duties into West Virginia law, connecting utility results back to the facilities contributing PFAS so that reduction can be pursued rather than only treatment.
Why is Parkersburg significant nationally?
The C8 Health Project that came out of the litigation there produced the epidemiological evidence that later health advisories and drinking water standards relied on. Most US PFAS regulation traces back to it.
Does West Virginia have its own MCL?
The enforceable drinking water numbers are the federal MCLs. The state statute adds sampling and source identification duties rather than a different limit.

Primary Sources

Data not supplied by Nelson. Every figure comes from public regulator records published by the agencies cited. Nelson compiles, maps and links the records, and does not create, verify, adjust or own the underlying data. This hub is a free public resource published to share knowledge. Every figure traces to a government dataset a reader can download and re-check, the sources are listed in the methodology, and nothing here is gated behind a form. Dataset compilation copyright 2026 Nelson Environmental Remediation Ltd. All rights reserved. Source attribution required for reuse. Data licence and citation.

WVDEP PFAS information

West Virginia Bureau for Public Health, Environmental Engineering

US EPA, PFAS National Primary Drinking Water Regulation (2024)

US EPA, PFOA and PFOS designated CERCLA hazardous substances (2024)

Other State Briefs

ALAlabamaFederal MCL implemented by ADEM; the pressure comes from Decatur-area manufacturing history and AFFF sites, not from a state number.

AKAlaskaFederal MCL for drinking water, state cleanup levels under 18 AAC 75, and logistics that make on site treatment the practical answer.

AZArizonaFederal MCL implemented by ADEQ, backed by one of the more thorough state sampling programmes and a long-running Tucson-area groundwater plume.

ARArkansasFederal MCL only; the site work sits at Little Rock Air Force Base, Ebbing Air National Guard Base and industrial legacy properties.

CACaliforniaSix-analyte notification framework; state MCLs in rulemaking; DTSC designating PFAS-containing wastes as hazardous.

COColoradoReg 31 groundwater and surface water standards; no state drinking water MCL; HB22-1345 product bans; Peterson SFB / Widefield AFFF community response ongoing.

See all 51 US jurisdictions in the PFAS Regulatory Tracker →

Contact

How can we help?

Project inquiries, technical consultation, or emergencies.

We respond to project inquiries within one business day.

Nelson Environmental Remediation

Head Office

30541 - 100 Avenue

Acheson (Edmonton), Alberta

Canada T7X 6L8

Phone

1.780.960.3660

Toll Free: 1.888.960.8222

Fax

1.780.962.6885

Email

Follow Us on LinkedIn →

More from Nelson

  • Mobile thermal technology: configured for the material, brought to site
  • How to use The Hub for contamination research
  • Navigator: a practical guide to remediation strategy
  • The Ground Truth: Warren Nelson's remediation newsletter
  • A new era of enlightenment
  • Value should be the final outcome
  • What’s next at Nelson
  • Why independent research matters more than anything
  • Over thirty years of permanent outcomes: a field review of Nelson’s project record
  • Petroleum-contaminated soil treatment in the US: build the plan around the fuel profile
  • Contaminated soil management in the US: from excavation to an accepted destination
  • US remediation project evidence: what Tioga and Honolulu tell a project owner

Site Navigation

  • All Articles & Research
  • Thermal Remediation Capabilities
  • Project Case Studies
  • Remediation Glossary
  • About Nelson Environmental Remediation
  • Contact Nelson