Florida PFAS Regulations: FDEP Cleanup Framework & Federal MCL Implementation

Federal MCL adopted; FDEP Provisional CTLs for cleanup; heavy DoD site burden.

Florida operates a two-track PFAS system: federal MCLs for drinking water and FDEP Provisional Cleanup Target Levels for site remediation. Peninsula geology and the density of active military airfields make the response inventory large and technically demanding.

Agency

Florida Department of Environmental Protection (FDEP)

Primary Statute

F.A.C. Chapter 62-550 (drinking water); Chapter 62-780 (contaminated site cleanup)

Rule Adopted

Federal MCL adopted 2024; PCTLs in place

Compliance

2029-04-26 (EPA proposed changes on 18 May 2026 that are not final)

Context

Regulatory Overview

Florida implements the federal PFAS NPDWR through FDEP's drinking water program without a competing state MCL. Compliance monitoring runs on the federal 2025 to 2027 initial monitoring window with 2029 compliance.

For contaminated sites, FDEP has published Provisional Cleanup Target Levels for PFOA (70 ppt for groundwater) and PFOS with a broader menu now under revision to align with the federal MCLs. Chapter 62-780 governs the site rehabilitation process from initial site assessment through Site Rehabilitation Completion Order.

DoD installations across Florida, Eglin AFB, Tyndall AFB, Patrick SFB, Whiting Field, NAS Jacksonville, NAS Pensacola, MacDill AFB, Homestead ARB, carry substantial AFFF plumes. The Florida karst geology accelerates plume migration and complicates natural attenuation strategies.

Water supply in Florida is drawn largely from the Floridan and Biscayne aquifers, both of which are shallow, transmissive and closely connected to surface water. That makes source protection the practical control: utilities have moved wellfields, blended supply and installed granular activated carbon rather than wait for plume capture. Municipal solid waste landfills add a second pressure point, since leachate carrying PFAS is routed to publicly owned treatment works that were never designed to remove it.

Numbers

State MCL vs Federal MCL

Compound

Florida

Federal (2024 NPDWR)

Note

PFOA70 PCTL (GW)4 pptPCTL under revision

PFOS70 PCTL (GW)4 ppt

PFHxSFederal10 ppt

PFNAFederal10 ppt

ppt = parts per trillion (ng/L). Where a state number is stricter, the state number controls; where the federal number is stricter, the federal number controls for public water systems.

History

Rulemaking & Response Timeline

2022FDEP publishes Provisional CTLs for PFOA and PFOS.

2024-06Federal NPDWR effective; FDEP implements through Chapter 62-550.

2025-2027Initial monitoring window for Florida PWS.

2026-2028Anticipated PCTL revision to align with federal MCLs.

Case Docket

Notable Enforcement & Response Cases

ongoing

Eglin AFB / Northwest Florida

AFFF plumes across the Eglin reservation impact multiple ranges; Air Force CERCLA response with FDEP concurrence continues.

ongoing

NAS Jacksonville / Cecil Field

PFAS plumes at the active NAS and former Cecil Field NAS reach off-base residential wells; Navy lead PRP with FDEP site coordination.

ongoing

Tyndall AFB / Panama City

PFAS investigation continues at Tyndall AFB alongside Hurricane Michael reconstruction; Air Force lead.

Compliance

Permit & Cleanup Pathways

Chapter 62-780 Site Rehabilitation with SRCOs.

Voluntary Cleanup Tax Credit Program.

FDEP Industrial Wastewater Permits (NPDES delegated) with PFAS conditions for high-strength dischargers.

Air construction permits for on-site thermal destruction units.

Obligations

Sampling & Reporting

PWS initial monitoring 2025 to 2027 per federal rule.

Chapter 62-780 site characterization for confirmed releases.

DoD federal facility schedules for base cleanups.

FAQ

Frequently Asked Questions

Does Florida have its own PFAS drinking-water MCL?
No. Florida implements the federal 2024 MCLs through FDEP's drinking water program and has not adopted separate state MCLs.
What is a PCTL?
A Provisional Cleanup Target Level is a numeric groundwater or soil value FDEP uses to determine whether a site meets cleanup requirements under Chapter 62-780; PFAS PCTLs are being revised to align with the federal MCL.
Are DoD PFAS sites Florida-regulated?
DoD sites operate under CERCLA with the military service as lead PRP; FDEP concurrence and enforcement applies to off-base impacts and treatment approvals.

Primary Sources

Data not supplied by Nelson. Every figure comes from public regulator records published by the agencies cited. Nelson compiles, maps and links the records, and does not create, verify, adjust or own the underlying data. This hub is a free public resource published to share knowledge. Every figure traces to a government dataset a reader can download and re-check, the sources are listed in the methodology, and nothing here is gated behind a form. Dataset compilation copyright 2026 Nelson Environmental Remediation Ltd. All rights reserved. Source attribution required for reuse. Data licence and citation.

FDEP PFAS

F.A.C. Chapter 62-550

F.A.C. Chapter 62-780

US EPA PFAS NPDWR

Other State Briefs

ALAlabamaFederal MCL implemented by ADEM; the pressure comes from Decatur-area manufacturing history and AFFF sites, not from a state number.

AKAlaskaFederal MCL for drinking water, state cleanup levels under 18 AAC 75, and logistics that make on site treatment the practical answer.

AZArizonaFederal MCL implemented by ADEQ, backed by one of the more thorough state sampling programmes and a long-running Tucson-area groundwater plume.

ARArkansasFederal MCL only; the site work sits at Little Rock Air Force Base, Ebbing Air National Guard Base and industrial legacy properties.

CACaliforniaSix-analyte notification framework; state MCLs in rulemaking; DTSC designating PFAS-containing wastes as hazardous.

COColoradoReg 31 groundwater and surface water standards; no state drinking water MCL; HB22-1345 product bans; Peterson SFB / Widefield AFFF community response ongoing.

See all 51 US jurisdictions in the PFAS Regulatory Tracker →

Contact

How can we help?

Project inquiries, technical consultation, or emergencies.

We respond to project inquiries within one business day.

Nelson Environmental Remediation

Head Office

30541 - 100 Avenue

Acheson (Edmonton), Alberta

Canada T7X 6L8

Phone

1.780.960.3660

Toll Free: 1.888.960.8222

Fax

1.780.962.6885

Email

Follow Us on LinkedIn →

More from Nelson

  • PFAS and the changing landscape: What site owners should know
  • LNAPL remediation regulations: How to identify the requirements for your site
  • Alberta Tier 1 soil and groundwater remediation guidelines: How to assess their applicability
  • Mobile thermal technology: configured for the material, brought to site
  • How to use The Hub for contamination research
  • Navigator: a practical guide to remediation strategy
  • The Ground Truth: Warren Nelson's remediation newsletter
  • A new era of enlightenment
  • Value should be the final outcome
  • What’s next at Nelson
  • Why independent research matters more than anything
  • Over thirty years of permanent outcomes: a field review of Nelson’s project record

Site Navigation

  • All Articles & Research
  • Thermal Remediation Capabilities
  • Project Case Studies
  • Remediation Glossary
  • About Nelson Environmental Remediation
  • Contact Nelson