Minnesota PFAS Regulations: Amara's Law, Health-Based Values & the 3M Consent Decree

Amara's Law product ban; MDH health-based values below federal MCLs; 3M Consent Decree still operative.

Minnesota anchors US producer-responsibility PFAS enforcement. Amara's Law (2023) drives the nation's most aggressive product phase-out, health-based values sit well below federal MCLs, and the $850M 3M Consent Decree funds East Metro drinking-water treatment through 2050.

Agency

Minnesota Department of Health (MDH); Minnesota Pollution Control Agency (MPCA)

Primary Statute

Minn. Stat. §116.943 (Amara's Law); Minn. R. 4717 (drinking water); Minn. R. 7050 (surface water)

Rule Adopted

Health-based values 2007 to 2024; Amara's Law effective 2025 (products) / 2032 (full ban)

Compliance

Amara's Law product bans 2025 → 2032; federal MCL 2029 (EPA proposed changes on 18 May 2026 that are not final)

Context

Regulatory Overview

Minnesota is the birthplace of PFAS manufacturing (3M, Cottage Grove) and has the country's longest continuous PFAS regulatory record. MDH promulgated Health Risk Limits (HRLs) under Minn. R. 4717.7860 in November 2023 for PFOA (7.9 ng/L), PFOS (2.3 ng/L), PFHxS (47 ng/L) and PFBS (2000 ng/L). These are enforceable and several are stricter than the 2024 federal MCL. MDH advised in June 2025 that systems use the federal 10 ng/L figure for PFHxS.

Amara's Law is the most ambitious PFAS product statute in the country: intentionally added PFAS is banned in 11 product categories starting January 1, 2025 (carpets, cookware, cosmetics, dental floss, fabric treatments, children's products, menstrual products, cleaning products, ski wax, upholstered furniture, textile furnishings), with a full ban on all avoidable uses by 2032. Manufacturers must report PFAS-containing products to MPCA.

The 2018 3M Consent Decree resolved Minnesota AG claims for natural-resource damages in the East Metro (Washington County). It committed $850M, the largest state-only PFAS settlement, for drinking water infrastructure that continues through 2050, funding GAC and IX treatment across Woodbury, Cottage Grove, Lake Elmo, Oakdale, and surrounding communities.

Numbers

State MCL vs Federal MCL

Compound

Minnesota

Federal (2024 NPDWR)

Note

PFOA7.9 (HRL)4 pptState HRL drives cleanup; federal MCL controls PWS

PFOS2.3 (HRL)4 ppt

PFHxS47 ppt10 pptMDH advised in June 2025 that systems use the federal 10 ng/L figure for PFHxS

PFBS2,000 pptMixture only

PFBA7,000 pptNot regulatedState-only HBV

PFHxA200 pptNot regulated

ppt = parts per trillion (ng/L). Where a state number is stricter, the state number controls; where the federal number is stricter, the federal number controls for public water systems.

History

Rulemaking & Response Timeline

20023M ceases PFOS production at Cottage Grove after internal risk review.

2007MDH issues first PFAS Health-Based Values.

2010Minnesota AG sues 3M for natural resource damages.

2018-02$850M 3M Consent Decree resolves NRD claims.

2021-2023PFAS Blueprint & Amara's Law enacted (SF 2310 / HF 2310).

2025-01First tier of Amara's Law product bans in force.

2029Federal MCL enforceable; layered onto state HBVs.

2032-01Full ban on avoidable PFAS uses under Amara's Law.

Case Docket

Notable Enforcement & Response Cases

2018 to date (through 2050)

Minnesota v. 3M, East Metro Consent Decree

$850M settlement funds long-term East Metro drinking water treatment. Priority-1 projects (Woodbury temporary treatment, Cottage Grove permanent GAC, St. Paul Park, Lake Elmo, Oakdale expansions) are being delivered on rolling schedules through the 2040s. Remains the largest state-only PFAS recovery in US history.

Public source

ongoing

MPCA vs. 3M Cottage Grove Site remediation

MPCA Site Response section oversees ongoing PFAS characterization and remediation at the 3M Cottage Grove facility and Woodbury, Oakdale, and Washington County Landfill legacy disposal sites, the source areas that drove the Consent Decree.

2021 to date

Metropolitan Airports Commission, MSP AFFF response

PFAS characterization at Minneapolis-St. Paul International following AFFF release investigations; coordinated with FAA-transitioning fluorine-free foam mandate.

Compliance

Permit & Cleanup Pathways

MPCA Voluntary Investigation and Cleanup (VIC) program pathway with PFAS-specific work plans.

MPCA industrial and municipal NPDES permits now include PFAS monitoring and, on new/reissued permits, effluent limits derived from surface-water HBVs.

MPCA solid waste and industrial waste rules govern PFAS-containing residuals, landfill acceptance is increasingly restricted for spent GAC/IX and AFFF-impacted soils.

MDH plan review for any PWS treatment addition (GAC, IX, RO) triggered by federal MCL or Consent Decree scope.

Obligations

Sampling & Reporting

PWS federal compliance monitoring 2025 to 2027; MDH parallel monitoring for HBV analytes not on the federal list (PFBA, PFHxA).

Amara's Law product reporting to MPCA due January 1, 2026 for any manufacturer selling PFAS-containing products into Minnesota.

NPDES-permitted industrial dischargers face escalating PFAS characterization requirements at permit reissuance.

FAQ

Frequently Asked Questions

Does Amara's Law apply to industrial users?
Amara's Law targets intentionally added PFAS in consumer product categories, not industrial process uses. However, manufacturers must report all PFAS-containing products sold in Minnesota to MPCA and the 2032 full ban covers any 'avoidable' use, which MPCA is defining broadly through rulemaking.
Are Minnesota's HBVs enforceable?
The four PFOA, PFOS, PFHxS and PFBS values are Health Risk Limits promulgated under Minn. R. 4717.7860 in November 2023 and are enforceable. Other HBVs, such as those for PFBA and PFHxA, are not MCLs but are treated as compliance drivers under MPCA's site response and permitting programs.
How does the 3M Consent Decree affect other PRPs?
The Consent Decree resolves state NRD claims against 3M only. It does not release other manufacturers, distributors, or downstream users; MPCA continues enforcement actions and cost recovery against other PRPs at legacy sites statewide.

Primary Sources

Data not supplied by Nelson. Every figure comes from public regulator records published by the agencies cited. Nelson compiles, maps and links the records, and does not create, verify, adjust or own the underlying data. This hub is a free public resource published to share knowledge. Every figure traces to a government dataset a reader can download and re-check, the sources are listed in the methodology, and nothing here is gated behind a form. Dataset compilation copyright 2026 Nelson Environmental Remediation Ltd. All rights reserved. Source attribution required for reuse. Data licence and citation.

MDH PFAS Program

MPCA PFAS Program

Amara's Law (Minn. Stat. §116.943)

3M Consent Decree

US EPA PFAS NPDWR

Other State Briefs

ALAlabamaFederal MCL implemented by ADEM; the pressure comes from Decatur-area manufacturing history and AFFF sites, not from a state number.

AKAlaskaFederal MCL for drinking water, state cleanup levels under 18 AAC 75, and logistics that make on site treatment the practical answer.

AZArizonaFederal MCL implemented by ADEQ, backed by one of the more thorough state sampling programmes and a long-running Tucson-area groundwater plume.

ARArkansasFederal MCL only; the site work sits at Little Rock Air Force Base, Ebbing Air National Guard Base and industrial legacy properties.

CACaliforniaSix-analyte notification framework; state MCLs in rulemaking; DTSC designating PFAS-containing wastes as hazardous.

COColoradoReg 31 groundwater and surface water standards; no state drinking water MCL; HB22-1345 product bans; Peterson SFB / Widefield AFFF community response ongoing.

See all 51 US jurisdictions in the PFAS Regulatory Tracker →

Contact

How can we help?

Project inquiries, technical consultation, or emergencies.

We respond to project inquiries within one business day.

Nelson Environmental Remediation

Head Office

30541 - 100 Avenue

Acheson (Edmonton), Alberta

Canada T7X 6L8

Phone

1.780.960.3660

Toll Free: 1.888.960.8222

Fax

1.780.962.6885

Email

Follow Us on LinkedIn →

More from Nelson

  • PFAS and the changing landscape: What site owners should know
  • LNAPL remediation regulations: How to identify the requirements for your site
  • Alberta Tier 1 soil and groundwater remediation guidelines: How to assess their applicability
  • Mobile thermal technology: configured for the material, brought to site
  • How to use The Hub for contamination research
  • Navigator: a practical guide to remediation strategy
  • The Ground Truth: Warren Nelson's remediation newsletter
  • A new era of enlightenment
  • Value should be the final outcome
  • What’s next at Nelson
  • Why independent research matters more than anything
  • Over thirty years of permanent outcomes: a field review of Nelson’s project record

Site Navigation

  • All Articles & Research
  • Thermal Remediation Capabilities
  • Project Case Studies
  • Remediation Glossary
  • About Nelson Environmental Remediation
  • Contact Nelson