NJ
State Regulatory Brief
EPA Region 2
First-in-nation PFNA MCL; five-manufacturer directive; hazardous substance designation.
New Jersey was the first US state to enforce an MCL for PFNA, the first to name five global PFAS manufacturers in a single directive, and the first to designate PFOA and PFOS as hazardous substances. It is the reference regime for producer-responsibility PFAS enforcement.
Agency
New Jersey Department of Environmental Protection (NJDEP)
Primary Statute
NJAC 7:10 (drinking water); Spill Act NJAC 7:1E; Site Remediation Reform Act
Rule Adopted
PFNA MCL Sept 2018; PFOA/PFOS April 2020
Compliance
In force; federal NPDWR from 2029 (EPA proposed changes on 18 May 2026 that are not final)
Context
New Jersey took an aggressive early stance. The 13 ppt PFNA MCL adopted in September 2018 was the first enforceable MCL for a PFAS compound in the US. Follow-on rulemakings in April 2020 set 14 ppt PFOA and 13 ppt PFOS MCLs, all lower than most contemporaneous federal advisories.
The 2019 statewide directive to Solvay, DuPont, Chemours, 3M, and Arkema is the most aggressive producer-responsibility action in US PFAS history. It ordered the five manufacturers to fund characterization, treatment, and long-term monitoring across all impacted communities regardless of admission of liability.
NJDEP formally designated PFOA and PFOS as hazardous substances under the Spill Act in 2020, unlocking cost-recovery authority and requiring characterization at all Industrial Site Recovery Act (ISRA) transactions.
Numbers
Compound
New Jersey
Federal (2024 NPDWR)
Note
PFOA14 ppt4 ppt
PFOS13 ppt4 ppt
PFNA13 ppt10 pptFirst-in-nation state MCL
PFHxSNot state MCL10 ppt
HFPO-DANot state MCL10 ppt
ppt = parts per trillion (ng/L). Where a state number is stricter, the state number controls; where the federal number is stricter, the federal number controls for public water systems.
History
2015-2018Drinking Water Quality Institute recommends PFNA, PFOA, PFOS MCLs.
2018-09PFNA MCL of 13 ppt effective, first in the US.
2019-03Statewide Directive to Solvay, DuPont, Chemours, 3M, Arkema.
2020-04PFOA (14 ppt) and PFOS (13 ppt) MCLs effective.
2020-06PFOA and PFOS designated hazardous substances under the Spill Act.
2023-06$392M Solvay consent order for West Deptford / Paulsboro.
2024-06Federal NPDWR effective; state MCLs continue to apply.
Case Docket
2019 to 2023
Statewide Directive ripened into a $392M consent order in 2023 covering PFAS characterization, treatment, natural resource damages, and community drinking water for the Paulsboro / West Deptford region.
1990s to date
Long-tail PFAS releases at the Chambers Works and Salem County sites remain under active DEP oversight; multiple consent orders and NRD claims outstanding.
2019 to date
3M included in the 2019 Directive; parallel state litigation continues alongside the AFFF MDL federal proceedings.
Compliance
ISRA compliance triggers PFAS characterization on any industrial establishment transfer.
Site Remediation Program under LSRP oversight for private cleanup.
NJPDES permit special conditions for high-strength industrial dischargers.
Air permits from NJDEP DAQ for on-site thermal treatment.
Obligations
Quarterly PWS compliance monitoring for PFOA, PFOS, PFNA.
Site-wide characterization on any Spill Act release notification.
ISRA General Information Notice and Preliminary Assessment obligations.
FAQ
Data not supplied by Nelson. Every figure comes from public regulator records published by the agencies cited. Nelson compiles, maps and links the records, and does not create, verify, adjust or own the underlying data. This hub is a free public resource published to share knowledge. Every figure traces to a government dataset a reader can download and re-check, the sources are listed in the methodology, and nothing here is gated behind a form. Dataset compilation copyright 2026 Nelson Environmental Remediation Ltd. All rights reserved. Source attribution required for reuse. Data licence and citation.
See all 51 US jurisdictions in the PFAS Regulatory Tracker →
Contact
Project inquiries, technical consultation, or emergencies.
We respond to project inquiries within one business day.